Avista extends review of large data center energy requests, pausing negotiations to incorporate public feedback and enhance planning processes.
Quiver AI Summary
Avista announced it will take extra time to assess energy service requests from new large data center developers in response to community concerns and the need for a coordinated planning process in partnership with governmental agencies. The company's negotiations with a potential 500MW data center developer are currently on hold as Avista aims to incorporate stakeholder feedback and ensure that its energy service aligns with regional interests. Avista emphasizes that while it is a crucial part of the project development process, multiple reviews and regulatory approvals are necessary before any project can proceed. The company pledges to prioritize existing customers, ensure system reliability, and conduct responsible growth while engaging with local leaders and communities throughout this complex evaluation process.
Potential Positives
- Avista is prioritizing stakeholder feedback by pausing negotiations, demonstrating a commitment to transparency and community engagement.
- The company recognizes the need for a coordinated planning process for large data center projects, which can lead to better regional infrastructure and collaboration.
- Avista reaffirms its guiding principles that ensure existing customers will not bear additional costs for new large customers, emphasizing customer protection and system reliability.
Potential Negatives
- The pause in negotiations for energy service to the potential 500MW data center developer indicates uncertainty and possible delays in large-scale project development.
- The need for additional time to align with partners and communities suggests potential shortcomings in Avista's initial planning and communication processes.
- Public concern and community interest regarding large data center developments may reflect a lack of confidence in Avista's ability to manage the project effectively and responsibly.
FAQ
What is Avista's recent announcement regarding data centers?
Avista is taking more time to evaluate energy requests from large data center developers due to community feedback and planning needs.
Why is Avista pausing negotiations with a data center developer?
Negotiations are paused to allow for community discussions and ensure alignment with regional priorities and planning processes.
How does Avista prioritize its existing customers in new projects?
Avista ensures that existing customers will not bear the costs of serving new large customers through established safeguards.
What principles guide Avista's evaluation of large data center projects?
Key principles include prioritizing customers, ensuring system reliability, requiring regulatory approval, and ensuring responsible growth.
How long has Avista been in operation?
Avista has served energy customers for over 137 years, focusing on economic health and energy reliability in the region.
Disclaimer: This is an AI-generated summary of a press release distributed by GlobeNewswire. The model used to summarize this release may make mistakes. See the full release here.
$AVA Insider Trading Activity
$AVA insiders have traded $AVA stock on the open market 5 times in the past 6 months. Of those trades, 0 have been purchases and 5 have been sales.
Here’s a breakdown of recent trading of $AVA stock by insiders over the last 6 months:
- JANET D. WIDMANN sold 7,400 shares for an estimated $285,875
- WAYNE O MANUEL (Senior Vice President) has made 0 purchases and 2 sales selling 3,378 shares for an estimated $134,427.
- BRYAN ALDEN COX (Senior Vice President) sold 1,768 shares for an estimated $71,040
- ALEXIS G. ALEXANDER (Vice President) sold 555 shares for an estimated $22,089
To track insider transactions, check out Quiver Quantitative's insider trading dashboard. You can access data on insider stock transactions through the Quiver Quantitative API insider transaction endpoint.
$AVA Revenue
$AVA had revenues of $570M in Q1 2026.
You can track AVA financials on Quiver Quantitative's AVA stock page.
You can access data on AVA stock through the Quiver Quantitative API.
$AVA Hedge Fund Activity
We have seen 192 institutional investors add shares of $AVA stock to their portfolio, and 181 decrease their positions in their most recent quarter.
Here are some of the largest recent moves:
- TWO SIGMA INVESTMENTS, LP added 564,146 shares (+124.9%) to their portfolio in Q1 2026, for an estimated $22,616,613
- NORTHWESTERN MUTUAL WEALTH MANAGEMENT CO removed 539,686 shares (-99.7%) from their portfolio in Q1 2026, for an estimated $21,636,011
- BLACKROCK, INC. removed 458,128 shares (-3.1%) from their portfolio in Q1 2026, for an estimated $18,366,351
- NORGES BANK removed 430,796 shares (-55.1%) from their portfolio in Q4 2025, for an estimated $16,602,877
- QUBE RESEARCH & TECHNOLOGIES LTD added 382,628 shares (+111.5%) to their portfolio in Q1 2026, for an estimated $15,339,556
- ASSENAGON ASSET MANAGEMENT S.A. removed 343,989 shares (-100.0%) from their portfolio in Q1 2026, for an estimated $13,790,519
- LSV ASSET MANAGEMENT added 296,810 shares (+135.3%) to their portfolio in Q1 2026, for an estimated $11,899,112
To track hedge funds' stock portfolios, check out Quiver Quantitative's institutional holdings dashboard. You can access data on hedge funds moves and 13F filings through the Quiver Quantitative API 13F endpoint.
$AVA Price Targets
Multiple analysts have issued price targets for $AVA recently. We have seen 4 analysts offer price targets for $AVA in the last 6 months, with a median target of $40.5.
Here are some recent targets:
- Michael Lonegan from Barclays set a target price of $42.0 on 06/04/2026
- Anthony Crowdell from Mizuho set a target price of $42.0 on 05/06/2026
- Julien Dumoulin-Smith from Jefferies set a target price of $39.0 on 01/28/2026
- Shahriar Pourreza from Wells Fargo set a target price of $37.0 on 01/20/2026
Full Release
SPOKANE, Wash., June 12, 2026 (GLOBE NEWSWIRE) -- Avista announced today it is taking additional time to evaluate the processing of energy requests from new large data center developers as it seeks to partner with governmental agencies on creating a clear and coordinated planning process and as the company considers additional stakeholder feedback.
Negotiations concerning energy service to this potential data center are now paused. The decision follows recent community interest and concern related to Avista’s previously announced Memorandum of Understanding (MOU) with the new 500MW data center developer.
“We’ve heard the questions and concerns from our customers, community members and local leaders, and we take that feedback seriously,” said Heather Rosentrater, Avista President and CEO. “This input has demonstrated a need for a broader coordinated planning effort, which Avista will actively participate in. As a regional energy provider, we are just one part of the project development process. We recognize that we need more time to align with our partners and communities in a way that is transparent, thoughtful and in the best long-term interest of our region.”
As a regulated utility, Avista is required to review requests for service, including large proposals like this. At the same time, the developer must secure all necessary permits for their project. No single entity decides if a project will proceed—multiple reviews and approvals are needed before a project may move forward.
Avista remains committed to collaborating with local leaders, regulators and community members. These conversations will help inform how large data center requests are considered moving forward and ensure alignment with broader regional priorities. For over 137 years, Avista has served large load energy customers that help support the economic health and vitality of the region.
What’s new now is the scale of the data center requests and level of public interest. These unprecedented projects require new considerations for planning and coordination for all entities involved.
Avista’s approach to providing energy service to any potential large data center development remains grounded in clear principles:
- Customers come first: Existing customers will not pay for costs of serving a new large customer. Safeguards will be in place to prevent shifting of expenses to current customers.
- System reliability is non-negotiable : There are required engineering studies and system upgrades that must be completed before any service begins.
- Regulatory approval is required: Any final service agreement must be reviewed and approved by state regulators.
- Growth must be responsible: Any large project must deliver net benefits for our customers.
These guiding principles have been central to Avista’s evaluation process and will continue to inform both the current pause and future decisions.
Projects involving large data centers are complex and involve multiple stakeholders beyond Avista, including developers, regional infrastructure partners, regulators and local communities. As the electric provider, Avista plays an important role in evaluating how a project could be served energy—but it is one part of a broader process that includes regulatory review, infrastructure planning and community input before any final decisions are made.
The company will continue to provide more information as it becomes available.
A bout Avista Corp.
Avista Corp. is an energy company involved in the production, transmission and distribution of energy as well as other energy-related businesses. Avista Utilities is the operating division that provides electric service to 429,000 customers and natural gas to 386,000 customers. Its service territory covers 34,000 square miles in eastern Washington, northern Idaho and parts of southern and eastern Oregon, with a population of 1.5 million. Alaska Energy and Resources Company is an Avista subsidiary that provides retail electric service in the city and borough of Juneau, Alaska, through its subsidiary Alaska Electric Light and Power Company . Avista stock is traded under the ticker symbol "AVA." For more information about Avista, please visit avistacorp.com .
To unsubscribe from Avista’s news release distribution, send reply message to [email protected] .
Contact:
Avista 24/7 Media Access (509) 495-4174
Media: Jared Webley,
[email protected]
Investors: Stacey Walters (509) 495-2046
[email protected]